Off-Grid Solar System Sizing Calculator

Size every major component of an off-grid solar system in one go. Enter your daily energy use, peak load, worst-month sun hours and days of autonomy to get the panel array, battery bank, inverter and charge controller.

THELOADCALCSB-04 · System Builder unit
Solar arraySB-04
2.40kW
Panels6× 400W
Battery bank16.7kWh
Battery at 48V347Ah
Inverter4,000W
MPPT controller80 A
PV current at battery50A
Sized for 80% depth of discharge (LiFePO4)
Daily energy use
Peak load
Sun hours (worst month)
3.5h/day
Days of autonomy
2.0days
System voltage
Panel rating

How the off-grid solar system sizing calculation works

Array W = Daily Wh ÷ (Worst-month sun hours × 0.75)
Battery kWh = Daily kWh × Days ÷ 0.8 ÷ 0.9
Inverter ≥ Peak load × 1.25
Controller A ≥ Array W ÷ Battery V × 1.25
  • Off-grid systems lose about 25% between panels and appliances: wiring, charge controller, battery round trip and inverter.
  • Battery sizing assumes LiFePO4 at 80% depth of discharge. For lead-acid, roughly double the battery.
  • Controller size is the array's current at battery voltage with a 25% safety margin. Very large arrays can be split across two controllers.

Frequently asked questions

What size off-grid system do I need for 6 kWh per day?

+

With 3.5 worst-month sun hours and 2 days of autonomy: about 2.4 kW of panels, a 17 kWh battery bank, a 4 kW inverter for a 3 kW peak load, and an 80A MPPT controller at 48V.

How much does an off-grid solar system cost?

+

A small cabin system starts around $3,000–5,000. A full-time home system typically costs $15,000–40,000, with batteries the largest share.

Do I need a generator with off-grid solar?

+

Most full-time off-grid homes keep a generator for long cloudy spells. It lets you use a smaller, cheaper battery bank.

Results are engineering estimates for planning. Confirm final designs against equipment datasheets and local electrical codes, and have high-voltage or grid-connected work checked by a licensed electrician.