A ground-mount array frees you from roof size, orientation and shading limits, and makes cleaning and snow removal easy. It is also a construction project: foundations, racking, trenching and grounding all matter. This guide walks through planning and building one.

Key takeaways

  • Site for full sun from about 9am to 3pm in winter, and as close to the equipment as practical.
  • Tilt near your latitude for year-round production, steeper for winter-heavy use.
  • Foundations (concrete piers, driven piles or ground screws) must suit soil, wind and snow loads.
  • Bond the racking and use buried conduit or direct-burial cable at the required depth.

Siting

  • Check winter shading from trees and buildings, since shadows are longest then.
  • Keep the array close to the batteries or inverter to limit cable cost and voltage drop. High-voltage strings make longer runs practical.
  • Check setbacks, permits and HOA rules.
  • Call your utility-locate service before digging.

Estimate production at your site with the solar production by location calculator, and compare roof vs ground with the ground mount vs roof calculator.

Tilt and row spacing

A tilt close to your latitude balances the year; latitude + 10-15° favors winter. Multiple rows need spacing so the front row does not shade the back row on winter mornings. Use the tilt angle calculator, seasonal tilt adjustment and row spacing calculator. Adjustable-tilt racks or trackers can add production.

Foundations and racking

FoundationProsCons
Concrete piersStrong, works in most soilsLabor, curing time
Ground screwsFast, no concreteNeeds suitable soil; specialized install
Driven pilesFast for large arraysEquipment needed
BallastedNo diggingHeavy, only on suitable sites

Use racking engineered for your wind and snow loads, and follow its foundation spacing. Most kits are aluminum or galvanized steel with listed bonding hardware.

Wiring and trenching

  1. Wire panels into strings at the array, using PV wire and MC4 connectors.
  2. Bring strings to a combiner or junction box with a disconnect at the array if required.
  3. Trench to the required depth (varies by code and cable type; conduit often 18 inches or more for many residential applications).
  4. Run conduit or direct-burial cable to the equipment, with pull boxes for long runs.
  5. Install surge protection at both ends of long runs.

Cable selection and voltage-drop checks are in the cable and connector guide.

Grounding

Bond all racking sections and panel frames, run an equipment grounding conductor with the circuit, and connect to a grounding electrode at the array as code requires. The grounding and bonding diagram shows how the pieces connect. For roof installs instead, see how to install solar panels, and for remote properties, the off-grid cabin guide.

Frequently asked questions

How far can a ground-mount array be from the house?

Hundreds of feet is common with high-voltage strings and properly sized cable. Low-voltage arrays need to be much closer to avoid large losses.

What angle should ground-mounted solar panels be?

About equal to your latitude for year-round output, steeper for winter-focused use.

Do ground mounts need permits?

In most areas, yes, for the structure and electrical work. Check with your local building department.

Plan your array layout