Hybrid Inverter with Battery Backup Wiring Diagram

Solar that keeps working in a blackout: grid, PV, battery and a backup loads panel all meet at the hybrid inverter.

Hybrid Inverter with Battery BackupBackup portUtility GridMeterMain PanelNon-backed loadsSolar Array6kWHybrid Inverter48V, 8kWBackup Loads PanelBattery48V 15kWhAC (hot/neutral)Data / senseSolar PV (+/−)DC positive (+)DC negative (−)theloadcalc.com
Simplified diagram. Ratings shown are examples; size components for your own system.Download PNG

A hybrid inverter combines a solar inverter, a battery inverter-charger and a transfer switch. Day to day, it powers your home from solar, charges the battery and exports any surplus. When the grid fails, it disconnects from the grid and keeps the backup loads panel running from solar and battery.

Key takeaways

  • Grid, PV, battery and backup loads all connect to the hybrid inverter.
  • The backup port feeds a separate backup loads panel. Non-backed loads stay in the main panel.
  • CT clamps on the grid conductors let the inverter measure import and export.
  • Battery communication (CAN or RS485) lets the inverter follow the battery's charge limits.

Components

ComponentTypical specRole
Hybrid inverter48V battery, 5-12kWSolar, battery and transfer
Solar arrayWithin the inverter's MPPT voltage/current limitsGeneration
Battery48V LiFePO4, 10-30kWh typicalStorage
Backup loads panelCritical circuitsStays on in outages
CT clampsOn grid service conductorsMeasure grid power
Grid breakerSized per inverter and panel rulesGrid connection

Step-by-step wiring

  1. 1Plan which circuits move to the backup loads panel, as in the critical loads subpanel diagram.
  2. 2Connect the inverter's grid port to a breaker in the main panel.
  3. 3Connect the backup port to the backup loads panel.
  4. 4Connect PV strings to the MPPT inputs through disconnects, and the battery through its breaker or fuse.
  5. 5Install CT clamps on the grid conductors with the arrow pointing as specified, and connect battery communications.
  6. 6Configure operating mode (self-consumption, backup reserve, time-of-use) and test grid-loss transfer.

Disconnect all sources before working, follow the equipment manuals and local electrical codes, and use a licensed electrician for work on home wiring and panels.

Operating modes

ModeWhat it doesGood for
Self-consumptionUses solar and battery first, grid lastLower bills
Backup reserveKeeps a set % for outagesStorm-prone areas
Time-of-useCharges cheap, discharges at peakTOU tariffs
Zero exportLimits export using CT readingsWhere export is not allowed

For storm planning, see hurricane power preparedness. To compare system types, see grid-tie vs off-grid vs hybrid, and for whole-home battery choices, the home battery backup guide.

Common mistakes

  • CT clamps installed backwards, so the inverter thinks you are importing when exporting.
  • Putting more on the backup panel than the inverter's backup rating.
  • Skipping battery communications, so the inverter cannot respect the battery's limits.
  • Expecting the main panel loads to stay on during outages.

Frequently asked questions

What is the difference between a hybrid inverter and a grid-tie inverter?

A grid-tie inverter only converts solar to grid power and shuts down in outages. A hybrid inverter also manages a battery and can power backup loads when the grid is down.

Does a hybrid inverter power the whole house in an outage?

Only the circuits on its backup port, unless it is sized and wired for whole-home backup.

What do CT clamps do?

They measure current flowing to and from the grid, so the inverter can maximize self-consumption or limit export.

Size your battery backup

See how long your battery will carry your backup loads.